Project Schedule:

  • 2021:  Design contract awarded, topographic survey and data collection

  • 2021 - 2022:  Regional storm drain data collection, hydrology analysis, and drainage report

  • 2022 - 2024:  Engineering plans finalized in preparation for construction, and right-of-way acquisition

  • 2024 - 2025:  Utility work by third-party utilities to relocate their facilities to prepare for construction

  • 2025 - 2027:  Project construction  â€‹â€‹

Current Project Exhibits:

Previous Project Exhibits:

Project Hotline: 602.532.6250

Adjacent City of Phoenix Project

Our colleagues at the City of Phoenix are also working on an adjacent project: The Happy Valley Road Improvement Project covers 67th Avenue to 35th Avenue. This project is managed by the City of Phoenix. For more information on that project, visit www.phoenix.gov/streets/happyvalley or use the project hotline of 623-825-3444 or email HappyValleyRoadSTR@phoenix.gov.