top of page
67 HV Intersection.JPG
Construction Info

67th Avenue Corridor - Construction Info

Current Construction Info:  (Oct. 29, 2026)

The City of Peoria has contracted with Sundt Construction for the 67th Avenue Corridor Improvement Project, Pinnacle Peak to Happy Valley Road, with the following work currently taking place or planned:

​

  • 67th Avenue traffic is currently reduced to one lane in each direction with left turns restricted, as needed, to accommodate work along 67th Avenue.

 

  • 67th Avenue traffic is currently shifted to the inside lanes, south of the Happy Valley Road intersection, as crews reconstruct the outside (curb lanes) of 67th Avenue. In addition, the main entrance to CCV and Lifetime Fitness will reopen with right-in/right-out access only scheduled for Tuesday, Nov. 3.​​​

Exhibit SEP 2024.png
  • Scheduled to begin Tuesday, Nov. 3 through approximately Tuesday, Dec. 22, 67th Avenue traffic will be shifted to the outside (curb) lanes for work to take place in the middle of 67th Avenue to reconstruct roadway and install a median island on the south side of the intersection. Left turns will not be permitted for northbound 67th Avenue onto westbound Happy Valley Road during this time.

​​

  • Crews are currently working on the east side of 67th Avenue near Chaminade to construct the wall, which is scheduled for painting the week of Nov. 2. Scheduled to begin Nov. 4, crews will install grates and pour concrete sidewalk, followed by installation of handrail, into late November.

 

  • Crews continue work in the Hatfield Road basin to install grates and also rip-rap to minimize erosion in the basin. Over the next several weeks, crews will install masonry columns and fence, and complete landscaping into December.

​

  • Crews continue work east of 67th Avenue, in the 65th Avenue wash, to install the spillway and gabion baskets, and continue grading to prepare for rip-rap installation in early December.

​

To accommodate the construction, speed limits on 67th Avenue, from Pinnacle Peak Road to Hatfield Road, are reduced to 30mph for the safety of travelers, construction crews, and nearby residents and businesses.

​

​​Access to residences and businesses is being maintained during this work, although it may not be the most direct route. Please be aware that construction schedules can be impacted by a variety of factors to include weather, materials scheduling, and availability of resources.  ​​Thank you for your patience during this work.​

Project Hotline: 602.532.6250

Adjacent City of Phoenix Project

Our colleagues at the City of Phoenix are also working on an adjacent project: The Happy Valley Road Improvement Project covers 67th Avenue to 35th Avenue. This project is managed by the City of Phoenix. For more information on that project, visit www.phoenix.gov/streets/happyvalley or use the project hotline of 623-825-3444 or email HappyValleyRoadSTR@phoenix.gov.

bottom of page