67th Avenue Corridor - Construction Info

Current Construction Info:  (May 8, 2025)

 

​To prepare for the City's improvements, APS and Southwest Gas contractor crews are currently working in the area to relocate their facilities out of the way of the planned improvements. APS is currently scheduled to be complete with their work in mid-May and Southwest Gas by the end of June. Roads remain open for travel with lane and left turn restrictions in place, as needed, to accommodate this utility work.

The City of Peoria has contracted with Sundt Construction for improvements to 67th Avenue, from Pinnacle Peak Road to Happy Valley Road, with work currently taking place for drainage improvements along Pinnacle Peak Road and Hatfield Road, west of 67th Avenue, as follows:

  • The New River Trail is currently CLOSED at Hatfield Road, between Pinnacle Peak and Happy Valley, through December 2026. This closure is necessary to accommodate excavation and installation of a 90” storm drain pipe to serve as the outfall for drainage during stormwater events.​

Exhibit SEP 2024.png

​

  • Scheduled to take place May 12 - 30, the Hatfield Road and 72nd Avenue intersection will be closed to traffic for storm drain pipe to be installed across the intersection. Detour signage will be in place to direct travelers around the closure. Paving back of the intersection is currently scheduled for June 2.

  • Following work in Hatfield Road across 72nd Avenue, storm drain pipe installation will continue in the south side of Hatfield Road, working east toward the 67th Avenue basin. To accommodate this work, Hatfield Road will be WESTBOUND only (no eastbound traffic permitted) during weekdays (Monday through Friday), and relaxed over the weekends slightly to permit two-way traffic on Saturdays and Sundays. This configuration is expected to be in place into September. As part of the work at 72nd/Hatfield, concrete crews will restore any needed valley gutters, driveways and curb and gutter. In addition, scheduled for mid to late June, crews will install storm drain manholes as part of the drainage improvements.  

  • Work also continues to trench and install 60” storm drain pipe in the north side of Pinnacle Peak Road, from the drainage basin at 70th Avenue to 67th Avenue. Pinnacle Peak Road remains open for travel during this work and resident access is being maintained. Following pipe installation, crews are working to restore driveways, as needed. Segments of the path at the retention basin on the northeast corner of 70th Avenue and Pinnacle Peak Road are closed to accommodate storm drain pipe installation at the southeast corner of the basin.

  • Scheduled to begin the week of May 12, crews will work in the Pinnacle Peak drainage basin to remove pipe and reconstruct two concrete headwalls, with this work taking 5-6 weeks to complete.

  • Also scheduled to begin the week of May 12, for approximately two weeks, prewetting will take place in the wash area between Hatfield Road and Saguaro Park Lane (Mountainview Ridge community), east of 67th Avenue to approximately 65th Drive. This effort is necessary to prepare the area for upcoming work after Memorial Day for pipe installation as part of the drainage improvements.

Access to residences and businesses will be maintained during this work. Please be aware that construction schedules can be impacted by a variety of factors to include weather, materials scheduling, and availability of resources.

​​

Thank you for your patience during this work.​