top of page
67 HV Intersection.JPG

Schedule & Exhibits

Current Project Schedule:

  • Design:  

    • Award of Design Contract in Summer 2021 COMPLETE

    • Topographic Survey & Data Collection in Summer/Fall 2021 COMPLETE

    • Regional Storm Drain Data Collection, Hydrology Analysis, and Drainage Report – Fall 2021 to Summer 2022 - COMPLETE

    • Preparation of Final Engineering Plans in Preparation for Construction – Summer 2022 to Fall 2024 - COMPLETE

    • Right of Way Acquisition for Widening 67th Avenue – ONGOING THROUGH 2024

​​

  • Construction:   Construction activities will be phased 2024 through 2027

    • Utility work for APS and Southwest Gas to relocate their facilities is scheduled to take place Fall 2024 Spring 2025.​

Current Project Exhibits:

Previous Project Exhibits:

bottom of page